SACRAMENTO, Calif. — After a year of turmoil capped by Calif. Gov. Gavin Newsom’s pledge in February to scale back California’s high-speed rail project, CEO Brian Kelly says he will unveil a new construction plan May 1 designed to restore flagging public confidence in the project.

The plan was devised by DB Engineering & Consulting, the U.S. branch of Deutsche Bahn, Germany’s national railway, which signed a six-year, $30-million contract at the end of 2017. This contact is expected to lead to the consulting company becoming the system’s first train operator. It is one of several DB recommendations for the project, including ways to save on capital expenditures, that will be incorporated in a report required by the state legislature on that date.

“I think (Deutsche Bahn) has been valuable and, in fact, I would intend to see their influence raised here,” Kelly said in an interview a month after returning to work following a medical leave that began last September.

It was for treatment of what he revealed was Guillain-Barré Syndrome, a rare and incurable ailment affecting the nervous system. Kelly said he suffered full respiratory failure and now speaks with the aid of a tracheotomy in his throat.

Under the new construction plan, Kelly said the 119 miles of railroad now being built between Madera and a point north of Bakersfield, Calif., will be extended to 170 miles from Merced all the way into Bakersfield. That will require construction between San Francisco and Gilroy to be postponed indefinitely so those funds can be shifted to the Central Valley.

But that operating line would make connections to Amtrak’s San Joaquin trains at Merced and an extension of the Altamont Corridor Express service planned on the Union Pacific from Lathrop to Merced and cut rail travel times substantially between Bakersfield and other Central Valley points to Sacramento, Oakland, and San Jose.

Such an initial operating segment of the system would convince Californians of the value of high-speed rail and lead to sufficient new investment to build from Madera to San Jose and San Francisco, Kelly argues.

“I know what I really need to show is (Silicon) Valley to (Central) Valley,” he said. “And I want to build valley-to-valley. But I believe we have options under the law that will allow an interim service before we get to valley-to-valley that will allow us to demonstrate the power of high-speed rail and what it can do.”

Kelly’s illness was the least publicized of several setbacks in the 15 months since he began the CEO’s job in January 2018.

His first day at work, the authority announced construction costs in the Central Valley had blown the budget by more than a third to $10.6 billion. The ensuing audit, ordered by the California Legislature, found widespread organizational flaws and poor contract management costing hundreds of millions of dollars.

Then, high-speed rail champion Jerry Brown’s tenure as governor ended and Newsom took office in January. In his February State of the State speech, Newsom left many people thinking the project was dead. Time magazine’s headline was “California Scraps Plan to Build High-Speed Railroad Between Los Angeles and San Francisco.”

The governor has since tried to re-explain what he meant. State Sen. Jim Beall, who chairs the transportation committee, called a hearing Feb. 11 to get more information on project plans. Shortly before he called the meeting to order, the state announced it had sold $600 million more in bonds to finance continuing construction.

“I did not hate the timing” of that announcement, Kelly said with a laugh. “My marching orders, I feel like, are getting trains on the ground in California, to stop talking about high-speed rail as an abstract concept, and let's show people what it can do. Then we expand.”

NEWSWIRETrains News Wire

  • Previous Day
  • April 05, 2019
  • Next Day
Leave a Comment
Want to leave a comment?
Only registered members of TrainsMag.com are allowed to leave comments. Registration is FREE and only takes a couple minutes.

Login or Register now.
Please keep your feedback on-topic and respectful. Trains staffers reserve the right to edit or delete any comments.
0 COMMENTS
FREE DOWNLOAD

FREE DOWNLOAD

The Genesee & Wyoming 

Newsletter Sign-Up

By signing up you may also receive occasional reader surveys and special offers from Trains magazine.Please view our privacy policy
Subscribe Up To 58% off the newsstand price!
Subscribe To Trains Mag Today
+